Friday, August 24, 2012

Drive way poured





 











Today the driveway was poured and will be cut Sunday or monday. Monday gone all the electrical was done the air con guys came put the vents in today, there's not much left to do. The few things to go is carpet, main floor tiling, change the handles as they put wrong ones in, mirror doors on wardrobes, kitchen appliances and outside just needs the air con unit.

Thursday, August 23, 2012

START OF A DRIVEWAY





 
Today they started the driveway we met Fred on site the concreter as we do most trades as its the only way you get things the way you want and there always happy to help and give you there advice. we changed from gunmetal to charcoal as its darker and matchers the bricks better. we also straightened the edging of the driveway up so now theres more driveway and doesnt go on any angles. Part of the fence was finished and inside the house bath, toilets, taps, towel rails, were installed along with the WRONG door handles as soon as i seen them i knew they wernt what we picked they look so ugly! so i rang Richard and he will fix it up.

Wednesday, August 22, 2012

FENCING ISSUES






Our nab put up there fence without contacting us, its left us with a bit of a head ake now as we need retaining walls, they used bricks but we want to do wood sleepers so might have to rip to fence up and start again. We were luckly that our 3 back nab all made contact and we got together and all agreed. we went 2 200x50 sleepers couldnt be happier.

Sunday, August 19, 2012

MIRRORS AND FITOUTS IN









Sunday visit home to be and we wernt exspecting any action on site till monday and the bathroom mirrors are on and fitout of cupboards are in, shower screens also done. Electrical is booked for tomorrow so that should see powerpoints downlights light fittings in.

Wednesday, August 15, 2012

SPOKE TO THE SS

Today we spoke to the ss Allan and he advised us if all goes well and theres nothing major we are 4-5 weeks away from completion next week the electrical, plumbing, fit outs are due the week after the drive way and council approvel and than at the very last carpet and our flooring as normaly the main floor tiles would be done already but we are doing black porcelain tiles and there very pricey.

Tuesday, August 14, 2012

PAINTING COMPLETED



Yesterday the painting was finished but finding out elderton only do one undercoat and one top coat we wernt happy about it so we payed the painter to do another coat and we also loved what the painter did in the media room so much we also had the wall cut out painted grey too which looks great. At the front of the house we have cladding and at the color selection it was surpost to be wattyle stained like the front door but it looked nothing like it and it wasnt even stained but painted brown so we also had that fixed today, we decided to paint it surfmist and it looks heaps better.

Thursday, August 9, 2012

GARAGE DOORS IN PAINTING ALMOST DONE

Over the past 3 weeks our painter Chris has been very busy doing all the painting internal and external we are very happy to have met him and he even painted our media room a different color to the rest of the house a dark grey and it looks magic we love it apart from the painting almost completed our garage doors went on yesterday next is main floor tiling carpets electrical fit outs than drive way.. We are also very happy that we get lots of sun thou out the house as we designed our home to the land and direction of the sun. We are on the home stretch!